We realized that much of our floor space was being occupied by empty crates from Van's Aircraft so on an off day Misters Jordan, Muhs and Brasch made a road trip to the dump!

Brian tries to avoid the cameras, so we got him from both directions.

Fun with glass cloth.

The session also included EAA Chapter 81 Board Member and retired mechanic Steve Horton inspecting and signing off a recent Service Bulletin that had been completed.

​Nick, now in college and working, stopped back to help out.

​On October 28th inventory started.

Old Nick and new Nick.

On December 9th and 10th, 2018 we did the final fitting of the wings to the fuselage.  Also continued with some minor engine work.  Group 2 has finished up Tail # 2, so they started preparing fiberglass for the canopy area.

​A little helper snuck in!

​Annabella from "Airplane # 2 Group" also helped out, learning how to use a micrometer and completing the steps for connection control cables.

​BINGO!

​We returned to work after the holiday break in January, 2019 getting the tail cone, among other things, mounted to the fuselage.

​Thanks to Jorge, a new inspection panel is installed.

​The resist to open the box could not be overcome, but the actual inventory will be completed later.

We safely drove in formation using the call signs "Dump One" and Dump Two".

​Our last work session of 2018 before the holiday break was mostly fiberglass prep work on the canopy area. 

​WOW!

On October 26, 2018 our engine arrived!

On April 2nd, 2018 our "finish kit" arrived.  The box had been delivered to Mr. North's business and, as seen below, Mr. North backs his truck up to the hangar with our latest box of parts.

Build dates continued in the new year in January on the 13th, 14th, 20th, 21st, 27th and 28th.  They included two more visits from Mr. Hobbs from Lightening West who helped with our canopy fiberglass.  Thank you again Mr. Hobbs!

Even though our build dates took a break over the holidays, we moved some airplane parts out to our donated hangar to make more room in our build site.

​While Jorge started working on tubing for the fuel system and Brian continued the finish work on the canopy, most of the activity was at the front of the airplane with the engine being hung.

​Inventory Complete!

​Inventory started 4/9/18!